Heijunka – How to Schedule High-Mix Production Without the Chaos
You’ve got 50 different products to make this week. Your MRP system says to run Product A for three days, then Product B for two days, then Product C…
Meanwhile, Customer X is screaming because their order of Product F won’t ship for six weeks. You’re drowning in work-in-process inventory. Your operators are bored running the same thing for days, then stressed switching to something completely different.
The schedule is a mess. Lead times are terrible. You’re constantly expediting.
There’s a better way.
It’s called mixed-model scheduling, and it lets you run different products in the same day—small batches, frequent changeovers, smooth flow—without chaos.
The result? Lead times drop 50-70%. Inventory drops by similar amounts. You can actually deliver what customers need, when they need it. This article will show you how.
What Is Mixed-Model Scheduling?
Mixed-model scheduling means running different products from the same family in small batches during the same production period—the same shift or the same day—sequenced to maintain steady flow.
Traditional approach:
Week 1-2: Product A (2,000 units)
Week 3-4: Product B (1,500 units)
Week 5: Product C (800 units)
Week 6: Product D (600 units)
Mixed-model approach:
Monday AM: Product A (100 units)
Monday PM: Product B (75 units)
Tuesday AM: Product C (40 units)
Tuesday PM: Product D (30 units)
Wednesday: Repeat cycle
Same weekly output. Completely different flow.
Why This Matters for High-Mix Operations
Traditional large-batch scheduling creates four big problems:
Problem #1: Long lead times
- Customer orders Product F (last in the rotation)
- Waits 8+ weeks while you finish Products A through E
- Customer goes to competitor
Problem #2: Massive inventory
- Must run huge batches (weeks of demand)
- Ties up hundreds of thousands in WIP
- What if demand changes?
Problem #3: Delayed quality feedback
- Make 2,000 of Product A
- Customer discovers defect in week 3
- All 2,000 potentially affected
- Massive rework or scrap
Problem #4: Boring work, then panic
- Operators run the same thing for days (monotonous)
- Then sudden changeover to something completely different
- No rhythm or flow
Mixed-model scheduling fixes all of this.
The Three Prerequisites
Before you can do mixed-model scheduling, you need three things in place:
Prerequisite #1: Product Families Defined
You must know which products are similar enough to run on the same equipment with minimal disruption. If you’re still trying to run every product on every machine, this won’t work.
Prerequisite #2: Quick Changeover (SMED)
Mixed-model means changing products multiple times per day. If changeover takes 3 hours, you can’t do this economically. Target: 15-30 minutes.
Prerequisite #3: Flowing Cells
Works best with cellular layouts where all operations for a family are together. Traditional functional layouts (all mills in one area, all lathes in another) make this harder.
If you don’t have these three, work on them first. Mixed-model scheduling is the culmination, not the starting point.
How to Implement Mixed-Model Scheduling (Step-by-Step)
Company: HVAC component manufacturer
Family: D
Step 1: Calculate Takt Time
Takt time = Available production time ÷ Customer demand
This tells you how fast you need to produce to meet demand.
Example:
- Product family demand: 400 units per week
- Available time: 2,400 minutes per week (40 hours)
- Takt time = 2,400 ÷ 400 = 6 minutes per unit
What this means: On average, you need to complete one unit every 6 minutes.
Step 2: Determine Batch Sizes
Start with daily demand for each product:

Rule of thumb: Batch size should be 1-2 days of demand (not weeks)
Adjust for changeover economics:
- If changeover is 20 minutes and batch takes 100 minutes to run, changeover is 20% of time (acceptable)
- If changeover is 20 minutes and batch takes only 40 minutes to run, changeover is 50% of time (too high—increase batch size)
Target: Changeover under 10-15% of run time
Step 3: Calculate “Every Product Every” (EPE) Interval
EPE tells you how often each product can run:
Formula: EPE = (Number of products × Average changeover time) ÷ Available time
Example:
- 4 products in family
- Average changeover: 20 minutes
- Available time: 480 minutes/day (8 hours)
- EPE = (4 × 20) ÷ 480 = 80 ÷ 480 = 0.17 days
Interpretation: Can run through entire family 6 times per day if needed
Target EPE:
- High-volume families: 0.5 days or less (multiple cycles per day)
- Medium-volume families: 1 day (every product daily)
- Low-volume families: 2-3 days (every product 2-3 times per week)
Short EPE = short lead time = high responsiveness
Step 4: Determine Optimal Sequence
The order you run products matters. Some transitions are smoother than others.
Create a changeover matrix:

Find the sequence that minimizes total changeover:
Option 1: A → B → C → D
- Total: 15 + 12 + 18 = 45 minutes
Option 2: A → D → C → B
- Total: 20 + 15 + 10 = 45 minutes
Option 3: A → C → B → D
- Total: 25 + 10 + 22 = 57 minutes
Best sequence: Options 1 or 2 (both 45 minutes)
Use this as your standard pattern.
Step 5: Create the Heijunka Board
Heijunka board = visual scheduling tool showing what to produce, when, and in what sequence
Basic layout:

The board shows:
- What to produce (which product)
- How much (batch size)
- When (time slots)
- Status (scheduled vs. completed)
Operators check the board to know what’s next. Supervisor updates as work completes. Everyone can see if you’re on track or behind.
Step 6: Execute and Adjust Daily
Daily routine:
Morning (before shift):
- Scheduler reviews yesterday’s performance
- Updates board with today’s schedule
- Adjusts for any issues (material shortages, equipment problems, new orders)
Throughout the day:
- Operators follow the sequence on the board
- Update status as each batch completes
- Signal problems immediately if falling behind
End of day:
- Review actual vs. planned
- Identify any problems
- Plan tomorrow
Every week:
Adjust batch sizes or sequence if needed
Review performance metrics
Discuss improvements
Real Example: Electronics Manufacturer
Company: Circuit board assembly
Products: 8 different control boards
Challenge: 6-10 week lead times, constant expedites, 62% on-time delivery
Before: Traditional MRP Scheduling
Approach:
- MRP generated work orders based on forecast
- Large batches (2-4 weeks demand per batch)
- Changed products weekly at best
Performance:
- Lead time: 6-10 weeks
- On-time delivery: 62%
- WIP: $280,000
- Changeover: 60 minutes (not optimized)
Customer impact:
- Couldn’t get quick responses
- Long lead times uncompetitive
- Constant expedite requests (which made things worse)
The Transformation
Step 1: SMED work (first!)
- Reduced changeover from 60 min → 18 min
- Standardized fixtures and procedures
- Made small batches economical
Step 2: Calculated parameters
- Family demand: 400 boards/week = 80 boards/day
- Available time: 420 minutes/day
- Takt time: 5.25 minutes per board
- Container size: 10 boards
- Pitch: 52.5 minutes ≈ 50 minutes
Step 3: Determined batch sizes
- Daily demand for each product (ranges from 5-20 boards/day)
- Batch sizes: 5-20 boards (1 day’s demand)
Step 4: Created heijunka board
- Sequenced to minimize changeover
- Every product runs 1-2 times per day
- Repeating pattern
Step 5: Implemented pull system
- Customer orders trigger kanban cards
- Cards placed on heijunka board
- Produce to actual demand (not forecast)
Results (After 4 Months)
Performance:
- Lead time: 6-10 weeks → 3-5 days (90% reduction)
- On-time delivery: 62% → 96%
- WIP: $280,000 → $45,000 (84% reduction)
- Inventory turns: 4× → 18× (4.5× improvement)
Operational:
- Every product runs daily or every other day
- Operators love the variety (less monotonous)
- Quality issues caught immediately (small batches)
- Can adjust to demand changes quickly
Financial:
- Working capital freed: $235,000
- Won new customers (competitors couldn’t match lead time)
- Reduced expedite shipping costs (was $8K/month, now under $1K)
- Capacity increased 35% (better flow, less changeover waste despite more changeovers)
Investment: $15,000 (SMED improvements, heijunka boards, training)
Payback: 3 weeks
The Heijunka Concept: Leveling Production
Heijunka (Japanese for “leveling”) is the practice of smoothing production by both volume and variety.
Level by volume:
- Produce at steady rate (not in spurts)
- Same total output every day
Level by variety:
- Distribute different products evenly
- Same mix of products every day
Why level?
For your operation:
- Predictable pace (operators know what to expect)
- Stable material consumption (easier for suppliers)
- Consistent equipment utilization
- Easy to spot and solve problems (variation is waste)
For customers:
- Short, predictable lead times
- Can order any product with confidence
- Flexibility in their planning
Traditional scheduling:

Heijunka scheduling:

Same weekly output (800 units), but smooth and predictable instead of chaotic.
Common Mistakes to Avoid
Mistake #1: Trying mixed-model without quick changeover
Mixed-model means frequent changeovers. If changeover takes 3 hours, you can’t run different products in the same day economically. Do SMED first.
Mistake #2: Making batches too large
“We’ll do mixed-model but run 2 weeks of each product.” That’s not mixed-model—that’s traditional scheduling with a fancy name. Batch sizes must be small (days, not weeks).
Mistake #3: No visual management
If the schedule lives in a computer and nobody on the floor can see it, it won’t work. The heijunka board must be visible, physical, and updated in real-time.
Mistake #4: Ignoring sequence
Running products in random order wastes changeover time. Sequence matters. Minimize total changeover.
Mistake #5: Not adjusting for reality
Material shortage? Equipment breakdown? Rush order? The schedule must adapt. Don’t blindly follow the board when conditions change.
Mistake #6: Overloading the schedule
Planning to 100% capacity leaves no buffer for variability. Target 75-85% utilization. The buffer isn’t waste—it’s flexibility.
Mistake #7: Poor coordination between cells
If Cell A feeds Cell B, they must be synchronized. Use supermarkets and pull signals to coordinate.
Runner-Repeater-Stranger: Different Products Need Different Strategies
Not all products should be scheduled the same way.
Runners (20% of products, 70% of volume):
- Ordered frequently (daily/weekly)
- High volume
- Predictable demand
- Strategy: Make to stock, schedule on heijunka board every day
Repeaters (30% of products, 25% of volume):
- Ordered regularly (monthly)
- Medium volume
- Somewhat predictable
- Strategy: Make to order, schedule when ordered (3-5 day lead time)
Strangers (50% of products, 5% of volume):
- Ordered rarely (few times per year)
- Low volume
- Unpredictable
- Strategy: Make to order, longer lead time acceptable (7-14 days)
Don’t treat all products the same. Runners get dedicated board slots. Repeaters fill available capacity. Strangers go to job shop or flexible area.
Integration With Your MRP/ERP System
Most companies have MRP. You don’t need to throw it away.
Use two-level scheduling:
Level 1: MRP handles planning (4-12 weeks out)
- Material planning (what to buy, when)
- Capacity planning (rough-cut)
- Customer order promising
- Work order generation
Level 2: Heijunka handles execution (1-5 days out)
- Daily sequencing (what to make today)
- Batch sizing (how much)
- Pull signals (replenishment)
- Visual management (execution on floor)
How they connect:
- MRP generates work orders (what needs to be made)
- Heijunka translates to daily schedule (when and in what sequence)
- As work completes, update MRP (closes loop)
Let each system do what it’s good at. MRP for planning, heijunka for execution.
The Business Case
What mixed-model scheduling delivers:
Lead time reduction:
- Typical: 50-70% reduction
- Small batches flow quickly
- Every product runs frequently
Inventory reduction:
- Typical: 50-70% reduction in WIP
- Small batches mean less waiting
- Frees up working capital
On-time delivery improvement:
- Typical: 15-30 percentage point improvement
- 70% → 95% is common
- Short lead times = easy to deliver on time
Quality improvement:
- Typical: 15-25% improvement in first-pass yield
- Small batches = problems caught immediately
- Not days or weeks later
Flexibility increase:
- Can respond to demand changes daily
- Can accept rush orders with minimal disruption
- Competitive advantage
Example ROI:
Payback: 2-3 weeks
WIP reduction: $300,000 freed up
Reduced expedite shipping: $50,000/year savings
Quality improvement value: $75,000/year savings
Revenue growth (won new business): $500,000/year
Investment: $20,000 (SMED, boards, training)
Your Next Step
Pick one product family. The one where lead times are killing you. The one where customers are frustrated with 8-week waits.
Make sure you have:
- Product family clearly defined
- Changeover reduced to 15-30 minutes (SMED)
- Cell layout that flows
Then implement mixed-model:
- Calculate takt time
- Determine batch sizes (start with 1-2 days demand)
- Find optimal sequence
- Create heijunka board
- Execute and adjust
Most companies see dramatic results within 8-12 weeks.
The hardest part isn’t the mechanics—it’s the change management. Getting schedulers to think differently. Getting operators comfortable with more frequent changeovers. Building discipline around the visual board.
If you want someone to guide you through this, that’s exactly what I do. I specialize in high-mix/low-volume manufacturing where mixed-model scheduling is the key to competitiveness. My approach is hands-on. We don’t spend months analyzing. We implement quickly—SMED first, then cells, then mixed-model scheduling. Fast results that stick.
Want to go deeper?
This article covers the basics, but my Book: Mixed-Model Scheduling: How to Level Flow and Orchestrate Production When Demand Changes Daily walks you through the complete implementation. [Get your copy on Amazon →]
Four ways I can help:
Remote Coaching Package – 10 hours of coaching with unlimited email support for specific challenges – $3,700.
Weekend Warrior Events – Focused 2-day on-site sessions for breakthrough results on a specific problem. Perfect for facilities that cannot afford to shut down production during the week – $9,500 (+ Travel).
Week-Long Kaizen Events – Complete system transformation in 5 days. We go from “current state” to “future state” in one week -$18,500 (+ Travel).
Full Consulting Projects – Month-long (or longer) intensive engagements for facility-wide transformation.
[BOOK FREE 30-MINUTE CONSULTATION] or [Download my Free 491-page Manaul] for the complete methodlogy.
The companies winning in high-mix environments aren’t the ones with the fanciest equipment. They’re the ones who’ve figured out how to create order from chaos. Mixed-model scheduling with heijunka is how you do that.